Home > Bond Project 2006 > What's Happening at Schools? > Nederland Middle/Senior High School  
Nederland Middle/Senior High School 
View of the front of Nederland Middle/Senior High School 
 

Nederland Middle/Senior High School
597 Eldora Road
Nederland, Colorado 80466
303-258-5888
http://schools.bvsd.org/nmshs
Original construction date: 1971

Report Updated:  10/22/2007 
Project Details

NOTE: MUOF/athletic improvements are being implemented in phase I. The rest of the project will be implemented in phase II.

Principal: Rich Salaz

Project Manager (building): To be determined

Architect (building): To be determined

Architect (MUOF/athletic): Davis Partnership

Project Manager (MUOF/athletic): Jenna Brummett

Contractor (building): To be determined

Contractor (MUOF/athletics): Hall Irwin

Project Budget (total): $5,546,645

Project Budget (MUOF/athletics): $2,192,561

Scheduled construction start date (building): To be determined

Scheduled construction start date (MUOF/athletic): June 7, 2007

Scheduled completion date (MUOF/athletic): 11/1/07

View expenditures to date

 

Design Advisory Team (DAT):

Will be determined in Phase II

Design Advisory Team (MUOF/athletics):

Completed

Project Timeline
MUOF/athletic improvements are being implemented in phase I. The rest of the project will be implemented in phase II.
Project Status
See below for pictures of work completed in Phase I
Scope of Work
 Facility Condition Assessment (FCA):  Planned implementation (FCA):
  •  HVAC improvements
  •  To be addressed in phase II
  •  Boiler replacement

 

  •  Exterior stucco repairs

 

  •  Intercom improvements

 

  • Electrical service and distribution improvements

 

  • Interior finish improvements (i.e. paint, carpet, flooring, ceiling tile, etc.)

 

  • Site pavement repair and replacement

 

  • Interior signage program
Program Compatibility Assessment (PCA): Planned implementation (PCA):
  • Counseling office improvements
  • To be addressed in phase II
  • Gym storage improvements

 

  • Science classroom addition/remodel

 

  • Physical Education classroom/multi-purpose addition

 

  • Expand administration office/conference space

 

  • General storage addition
Multi-Use Outdoor Facilities (MUOF): Planned implementation (MUOF):
  • Convert football/soccer field to synthetic turf
  • Work completed in Phase I!  See below for photos
  • Provide a paved all-weather running track

 

  • Provide new concessions, restrooms, and athletic storage building

 

  • Extend water and sewer utilities to the stadium area 

 

  • Upgrade the east playfield by removing the dirt infield
Information Technology (IT):

Planned implementation (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Extend WAN to building, upgrade head end equipment.
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Upgrade existing LAN distribution.
  • Implement VoIP to enhance communications capabilities and reduce cost
  • Install new VoIP telecommunications system

 

 

 Completed Work

 Completed construction work  Completed construction work
 Completed construction work  Completed construction work
 Completed construction work  Completed construction work