Lafayette Elementary School 
Lafayette Elementary School 
 
Lafayette Elementary School
101 North Bermont
Lafayette, Colorado 80026
303-665-5046
http://schools.bvsd.org/lafayette
Original construction date: 1964
Report Updated:  6/11/2008 
Project Details

Principal: Holly Hultgren

Architect: Barker Rinker Seacat
 
Project Manager: Tom Blahak

Contractor: Mark Young

Project Budget: $3,009,587

View expenditures to date

 

Design Advisory Team:

Staff
Holly Hultgren, Principal
Caleb Melamed
Betsy Kolber
Mary Waddell
Mark Cruthers
Parents
Stacie Sniff
Mark Sniff

DAT Meeting Schedule:

2007 
May 9
May 23
June 13
August 8
September 12 – Back to School Night
September 18 – PTA Presentation
November 27
December 18 (final)

Contact the DAT: DAT.Lafayette@BVSD.org

Project Timeline

Scheduled Milestones
Schematic design due 07/07; Completed 07/07
Design development drawings due 08/07; Completed 08/07
Construction documents due 11/07; adjusted due date 12/07; Completed 12/07
Hard bid scheduled 12/07; adjusted to 01/08; Completed 01/08
Construction scheduled 01/08 - 08/09; Currently under construction

Project Status

Click here for construction update.

Novedades del Proyecto de Construcción.

Activity that has occurred this period:

Completed exterior masonry, roof and drywall for classroom addition and multi-purpose room. Moved administration into portable.

Activity planned for next period:

Begin foundation work for administrative suite and new entry. Classroom addition and multi-purpose room will be completed for the start of school in August. Interior systems upgrades will be completed by August.  

Pending issues:

None.

 Budget status:

Within budget.

Schedule status:

On schedule to complete October 2008.

 ‭(Hidden)‬ Project Schedule

Chart of progress on the Lafayette Elementary School project
Scope of Work
Facility Condition Assessment (FCA):

Planned implementation (FCA):

  •  Communication systems improvements
  •  Replace / renovate Public Address system
  •  Ventilation improvements 
  •  In new construction and Administration area renovation, add conditioned air to Computer lab 131 as an alternate
  •  Irrigation system upgrades
  •  Replace 50% of irrigation system (alternate)
  •  Interior finishes upgraded (i.e. ceiling tiles, carpet and wall finishes, etc.) 
  •  In new construction and renovation, possibly corridors as an alternate
  • Upgrade electrical service and distribution
  • Add surge protection to main panel and 3 power panels, upgrade incoming service.
  • Interior Signage Program
  • Install new exterior lighting and renovate/replace interior signage

 

Program Compatibility Assessment (PCA): Planned implementation (PCA):
  • Provide small group instructional spaces
  • Add new 1,767 sf multi-purpose room (alternate)
  • Provide additional staff office space
  • Add 1211 sf, remodel 1,049 sf at main office
  • Provide additional classrooms
  • Add 4800 sf 4 classroom unit
Multi-Use Outdoor Facilities (MUOF): Planned implementation (MUOF):
  • Upgrade playground surfacing, equipment, and fencing
  • Future work
  • Provide adequate curbing and drainage
  • Future work
  • Replace aged and/or unsafe playground equipment
  • Survey ongoing
  • Make playgrounds ADA accessible
  • Survey ongoing
Information Technology (IT): Planned implementation (IT):
  • Upgrade WAN to provide capacity to support applications with high bandwidth demands 
  • Extend WAN to building, upgrade head end equipment.
  • Upgrade LANs to provide reliable and responsive access to data, research, and information 
  • Upgrade existing LAN distribution.
  • Implement VoIP to enhance communications capabilities and reduce cost
  • Install new VoIP telecommunications system.

 

 

 Content Editor Web Part

 

Construction photos April 2008


Classroom addition

 
Classroom addition interior

 
Multi-pupose room addition


Fifth graders in Caleb Melamed's class learn about construction and tour the project.

 

 

 

 
Construction photos - May 2008

 
Classroom addition

 
Classroom addition


Construction photos - June 2008

 
Classroom addition (looking north)

 

Classroom addition (looking west)

 
Classroom addition (looking east)



Multi-purpose room



Excavation for new administration and entry



Excavation for new administration and entry