Original construction date: 1954
Report Updated:   
Project Details

 Program Capacity

 Student Enrollment

 Bond Project Budget

18

13

$157,279

Design Advisory Team (DAT):  A design advisory team will be created when this project starts in phase II.

Project Timeline
Project Status
This project is scheduled for phase II.
Scope of Work

Facility Condition Assessment (FCA):

  • Electrical service improvements
  • Clock systems improvements
  • Roof replacement and repairs
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc.)
  • Correct site drainage issues
  • Replace interior doors

Program Compatibility Assessment (PCA):

  • None identified

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Wide area network upgrades
  • Upgrade LANs to provide reliable and responsive access to data, research, and information