Horizons K-8 School
4545 Sioux Drive
Boulder, CO 80303
303.447.5580
http://horizonsk8school.org
Original construction date: 1959
Report Updated:  9/22/2011
Project Details

Principal: Sonny Zinn

Architect: SLATERPAULL  

Project Manager: John Bollinger 

Contractor: Adolfson and Peterson

Original Project Budget:

 $2,500,000

 Supplemental Funds

 +$900,000

Revised Project Budget:  

$3,400,000

Horizons K8 project expenditures

Bond Program expenditures

Design Advisory Team (DAT): 

Staff
Sonny Zinn, Lead Teacher
Elizabeth Coleman
Jim Freund
Peter Hegelbach
Wendy Thoresen

Parent
Rosemary McKnight

Meeting Schedule

Sept. 30, 3:30 p.m.
Oct. 14, 3:30 p.m.
Nov. 18, 3:30 p.m.

Meeting Minutes

Contact the DAT 

Project Timeline
Scheduled Milestones
u
SD (schematic design) due 09/10; Completed 09/10
uDD (design development) drawings due 10/10; Completed 10/10
uCD (construction documents) due 01/11; Completed 12/10
uBid due 01/11
uConstruction scheduled 02/11 - 12/11; Completed 09/11
 
 

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
Project complete.
 
 
September 2011
 

 
New gym exterior


New gym and classroom addition 

 
New gym interior

 

 
New stage

 


New kindergarten classroom 

 
 
 
June 2011
 

 

 

 

 

 

 

 

 

 

 

 

May 2011
 

 

 

 

 

 

 

 

 

 
 
April 2011 
 
 

 

 

 

 

 
 
 
March 2011
 

 

 

 

 
 
 

 
 
Scope of Work

Facility Condition Assessment (FCA):

  • Communication systems improvements
  • Ventilation improvements
  • Irrigation system upgrades
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc.)
  • Upgrade electrical service and distribution
  • Interior Signage Program

Program Compatibility Assessment (PCA): (Amended by the Board of Education, April 13, 2010)

  • Kindergarten improvements
  • Add science labs (Not funded from current Bond Program)
  • Add art and music rooms (Not funded from current Bond Program)
  • Expand gym /cafeteria (Cafeteria not funded from current Bond Program)
  • Computer lab expansion (Not funded from current Bond Program)
  • Add IMC (Not funded from current Bond Program)
  • Administrative offices expansion (Not funded from current Bond Program)

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs

*The final determination of overall campus improvements will be determined as the charter school completes its facility master plan.