Flatirons Elementary School 
View of front of Flatirons Elementary School 
Flatirons Elementary School
1150 7th Street
Boulder, CO 80302
720.561.4600
http://schools.bvsd.org/flatirons
Original construction date: 1956
Report Updated:  9/30/2009 
Project Details

Principal: Scott Boesel

Architect: Larson Incitti

Project Manager: Rex Hartman

Project Budget: $4,203,473 

Flatirons Project Expenditures 

Bond Program expenditures

 

Design Advisory Team (DAT):

Staff
Scott Boesel, Principal
Stephanie Dolan
Robin Evans
Meg Harlow
Fran Klein
Lisa Morell
Jan Osburn
Mary Van Allen
Sally Wulffe

Parents 
Kevin Cooney
Beth Pommer
Terry Rodrigue
Josie Varga
Henry Vellands
John Wyatt
Melissa Zell

Contact the Flatirons DAT

DAT Meeting Schedule:

2008
April 30
May 14
May 28
September 17

Flatirons DAT Meeting Minutes 

Project Timeline

Scheduled Milestones
uSD (schematic design) due: 06/08; Completed 07/08
uDD (design development) due: 08/08; Completed 08/08
uCD (construction documents) due: 11/08
uHard Bid: 01/09
uConstruction Scheduled: 01/09 - 08/09; Completed 08/09

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
Scope of Work

Facility Condition Assessment (FCA):

  • Intercom improvements
  • Electrical service and distribution upgrades
  • Interior finish upgrades (i.e. paint, carpet, ceiling tile, flooring, etc.)
  • HVAC upgrades
  • Interior cabinet upgrades
  • Interior Signage Program

Program Compatibility Assessment (PCA):

  • Classroom additions
  • Art and music room additions/remodel
  • Expand gym/stage
  • Special Education classrooms
  • Expand administration/student health space
  • Cafeteria improvements

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs

Construction photos - April 2009

 

 

 

      

 

Construction photos - June 2009

 
New gym

 
New gym

 
New gym



Construction photos - August 2009

 
New main office and entryway

 

 
New teachers' lounge and workroom

 

 
Remodeled art room

 

 
New cafeteria converted from old gym

 

 
New gym

 

 
New playground equipment

 

 

 
New gym exterior