Centaurus High School 
Centaurus High School 
 
Centaurus High School
10300 South Boulder Road
Lafayette, Colorado 80026
303-665-9211
http://schools.bvsd.org/centaurushigh
Original construction date: 1973
Report Updated:  7/17/2008 
Project Details

Principal: Rhonda Haniford

Project Manager (building): Tom Blahak
Project Manager (MUOF/athletics): Joe Gierlach 
 
Architect (building): CSNA Architects
Architect (MUOF/athletics): Davis Partnership 
  
Contractor: Brown Schrephferman
Contractor: Golden Triangle Construction 
 

Original Total Project Budget

 $5,683,991

Supplement from Bond Program reserve to MOUF/Athletic budget for field house/site improvements

+ $400,000

Revised Total Project Budget

 $6,083,991

View expenditures to date
 

Design Advisory Team (building):

Staff
Rhonda Haniford, Principal
Paul Roper, Assistant Principal
Nancy Ossorio
Deborah Hammock
Diana Wiant
Dave Platt
Michael Hollenbach

Parents
Dave Slone

Meeting Schedule

2007
May 9
May 18
May 29
September 25
October 17 (final) 

Design Advisory Team (MUOF/athletics):

Staff
Chad Senseney
Ken Ebersole
Paul Roper
Deirdre Pilch
Michele DeBerry
Clarence Richardson
Owen Lunz
Phil Bravo
Mark Sibley
Rhonda Haniford

Contact the DAT:   DAT.Centaurus@BVSD.org

Project Timeline

Scheduled Milestones (building)
Schematic design due 07/07; Completed 06/07
Design development drawings due 08/07; Completed 08/07
Construction documents due 10/07; Completed 11/07
Hard bid scheduled 11/07; Bid opening 12/20/07, under budget
Construction scheduled 01/08 - 08/09, adjusted start 02/08; Currently under construction

Scheduled Milestones (athletic)
Construction scheduled 04/08 - 8/08; Currently under construction

Project Status

Construction Update

Activity that has occurred this period (building):

Concrete work on 2-story addition completed. Begin interior work.

Activity that has occurred this period (MUOF/Athletics):

Continue construction.

Activity planned for next period (building):

Continue construction on the 2-story addition. Demolish and remodel classrooms and counselors offices. Administrative offices will move to the student commons area. Demolition and renovation work will begin on the administrative suite. All work except the administrative suite will be completed by the start of school.

Activity planned for next period (MUOF/athletics):

Improvements to athletic facilities will be completed by July.

Critical issues (building):

None.

Critical issues (MUOF/athletics):

None.

 Budget status (building):

Within budget.

Budget status (MUOF/athletics):

Within increased budget.

Schedule status:

On schedule.

Scope of Work
Facility Condition Assessment (FCA):  Planned implementation (FCA):
  • HVAC upgrades
  • Improve air circulation at boys & girls locker rooms, increase combustion air at boiler rooms
  • Electrical branch wiring improvements
  • Add surge protection where needed and replace fire alarm devices 
  • Clock, fire alarm, and intercom systems improvements
  • Replace master clock and make improvements to public address system 
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc.)
  • Selected Improvements in renovation work plus sound control in commons area 
  • Roof replacement and repairs
  • Selected Improvements in renovation work 
  • Restroom renovations including ADA accessibility where required
  • Selected Improvements in renovation work 
  • Site irrigation system improvements
  •  Under MUOF portion, replace 50% of irrigation system
  • Interior signage program
  •  New interior signage for rooms, alternate 
  • Site paving replacement and repair
  • Site paving replacement and repair in new construction
  • Exterior wall repair
  • Exterior wall repair in new construction
   
 Program Compatibility Assessment (PCA):  Planned implementation (PCA):
  • Provide an applied technology lab facility
  • Add 5400 sf 2-story building, renovate rooms 112,113,114 of DaVinci Program 
  • Provide additional Special Education classrooms and offices
  • Renovate teachers offices, Remodel Multi-Intensive, SIED & SPED classrooms
  • Renovate and expand the art facilities
  • Remodel 5200 sf 2-D & 3-D Art rooms
  • Expand and renovate the administrative and counseling offices 
  • Add 860sf & Remodel 3050 sf at Administration area
   
Multi-Use Outdoor Facilities (MUOF): Planned implementation (MUOF):
  • Provide a home and visiting team field house
  •  Construction Drawings complete.
  • Provide six tennis courts
  • An all weather walk path is going to extend from the parking lot to the tennis courts at the South end of the campus. The existing tennis courts are to be resurfaced and three new courts are to be added adjacent to the existing courts. 
  • Bleacher area improvements to paving and drainage
  • The drainage is to be improved at the Northwest end of the football stadium to reduce ponding in the area. 
  • Resurface the running track
  • The existing running track is to be resurfaced. Bid documents issued. Bids due February 5, 2008.
Information Technology (IT): Planned implementation (IT):
  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Extend WAN to building, upgrade head end equipment. 
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Upgrade existing LAN distribution.
  • Implement VoIP to enhance communications capabilities and reduce cost
  • Install new VoIP telecommunications systems.

 

 

 

 

 

 Project photos

Groundbreaking February 7, 2008

Design Drawings

Construction photos March/April, 2008


Two-story addition


Two-story addition


Two-story addition

Construction photos - April, 2008


Two-story addition

 
Two-story addition

Construction photos - May, 2008


Two-story addition


Two-story addition

Construction photos - June, 2008


Two-story addition


Two-story addition


Field house foundation


Tennis court concrete pour

Construction photos - July, 2008

 
Two-story addition exterior

 
Two-story addition exterior


Two-story addition exterior 

 
Interior remodel

 
Interior remodel

 
Interior remodel