Birch Elementary School 
Front of Birch Elementary 
 
Birch Elementary School
1035 Birch Street
Broomfield, Colorado 80020
303.469.3397

http://bvsd.org/schools/birch
Original construction date: 1972
Report Updated:  10/5/2009 
Project Details

Principal: Tracy Stegall

Project Manager: Dave Jorschumb

Architect: OZ Architecture

Contractor: Adolfson and Peterson

Project Budget: $4,200,702

 

Design Advisory Team Members

Staff
Tracy Stegall, Principal
Tammie Hill
Tom Schiola
Kim Hohensee
Beth Murphy
Lisa Boston
Kort Hedges

Community Member
Ellie McKinley

Parents
Gabriella Ruelez
Lisa Abeyta
Denise Sorensen

Contact the Birch DAT

DAT Meeting Schedule

2009
April 8, 15, 29: 3 p.m.
May 13: 3 p.m.
July; TBD ONLY if necessary
September 2: 3 p.m.
October 28: 3 p.m. ONLY if necessary

Birch DAT Meeting Minutes

 

Project Timeline

Scheduled Milestones
uSD (schematic design) due 05/09; Complete
uDD (design development) drawings due 07/09; Complete
uCD (construction documents) due 09/09; Complete
uConstruction Scheduled 01/10 - 08/10

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
The construction drawings are complete. Construction is scheduled to begin in January.
 
Scope of Work

Facility Condition Assessment (FCA):

  • Fire alarm replacement
  • HVAC upgrades
  • Electrical service and distribution improvements
  • Interior finish improvements (paint, carpet, flooring, ceiling tile, etc.)
  • Irrigation system replacement
  • Selected exterior window replacement
  • Roof replacement
  • Replace boiler
  • Interior Signage Program

Program Compatibility Assessment (PCA):

  • Music and art room improvements
  • Enlarge library
  • Expand administration office and health room
  • Provide small group teaching spaces
  • Provide kindergarten remodel
  • Provide additional classrooms
  • Improve open space classroom acoustics

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs