Principal: Jennifer Rocke
Architect: Lantz-Boggio Architects
Project Manager (building): Tom Blahak
Project Manager (playground): Jim Williams
Contractor (building): Adolfson & Peterson
Contractor (playground): Goodland Construction
Original Project Budget: $2,850,862
Revised Project Budget: $3,204,192
| Original building budget |
$2,753,047 |
| Transfer to playground budget for irrigation |
-$83,981 |
| Transfer from Program Reserve for asbestos abatement |
+$353,330 |
| Transfer from Program Reserve to meet scope |
+$40,000 |
| Return to surplus |
-$5,853 |
| Revised building budget |
$3,056,542 |
| |
|
| Original playground budget |
$97,815 |
| Transfer from building budget for irrigation |
+$83,981 |
| Revised playground budget |
$181,796 |
Louisville Elementary building project expenditures
Louisville Elementary playground project expenditures
Bond Program expenditures